UPDATES: |
4/1/08 - We had 8 inches of snow on the site!! How fun is
that? :)
|
|
|
5/3/08 - We'll
be putting the in-floor heat system in today and basement
floors
will
be poured next week. On ward and Up ward we go!! |
|
|
6/4/08 - We will be putting on the various roof systems in early June - stop by
any
time to see how things are going together!!
|
| |
7/1/08 - The outside is nearly completed at this time, this
month we will work
on
interior walls, stop by to visit any time!! |
| |
7/31/08 - Winds at 84 miles an hour today peeled our new
shed like a tin can,
but
the house stood like a rock! We're on interior
walls, will be staining the
outside in
August and getting final grade dirt work done
around the house.
Visit any time,
we love to show the home even though it's
not quite done yet!! |
| |
9/9/08 - We are taping windows and will be putting finish on the interior then
moving to flooring and cabinets later this month. Hope to be in the house by
Mid-October!! |
| |
10/16/08 - We’ve moved in on the main floor and are now working in the basement.
We love to show people the home, so please call anytime to visit!! |
| |
12/16/08 -
The house is
completed
And snow has landed
The Blessings of 2008
We won't take for granted!!
Happy Holiday's
everyone!! |